RALEIGH – North Carolina regulators issued a final air-quality permit for Carolina Lithium, adding conditions after public comment to a proposed Gaston County mine and processing complex while leaving construction dependent on zoning, financing and other steps.
The Department of Environmental Quality said the major-source Title V permit covers emissions from mining, crushing and handling spodumene ore and from processing the ore into lithium hydroxide. The proposed facility is operated by Piedmont Lithium Carolinas Inc. and is now part of Elevra Lithium’s project portfolio.
DEQ held a 42-day comment period and an Oct. 13 public hearing before issuing the permit Nov. 13. In response to comments, the final permit restricts the facility’s ability to process spodumene mined away from the site. It also requires additional sampling to determine the elemental makeup of the mine’s ore before processing plants can begin operating.
The permit bars the company from changing the property boundary used in the state’s air-dispersion model. DEQ said it reviewed recent land sales and confirmed that the facility retains legal access to all parcels included in that analysis.
Potential emissions of particle pollution, nitrogen oxides and carbon monoxide each exceeded thresholds requiring a federal Prevention of Significant Deterioration review. DEQ said its modeling found that emissions controlled with the required technology are expected to maintain compliance with federal air-quality standards.
The permit requires controls to keep fugitive dust from leaving the site. It also caps hazardous air pollutants below 10 tons per year for any single pollutant and below 25 tons per year in total, levels that classify the operation as a minor source for those pollutants.
Carolina Lithium received a state mining permit in 2024 for a proposed 1,548-acre operation. Elevra told the Securities and Exchange Commission on Nov. 17 that the air permit was the project’s final statutory permit, but the filing does not describe an immediate construction start.
The company said it is preparing a new scoping study, expected in the second half of 2027, to determine the development approach. A construction decision remains subject to the study, rezoning, project financing and partnership arrangements. DEQ separately said the project must comply with applicable local zoning rules before construction or operation.
Sources
- North Carolina Department of Environmental Quality – Nov. 13 final air-permit announcement
- Elevra Lithium Form 6-K filed with the Securities and Exchange Commission, Nov. 17
- Mining Weekly – Nov. 18 report on permitting and the planned scoping study
Photo Credit: omid roshan via Unsplash, free to use under the Unsplash License. File photograph of an open-pit quarry; used as general mining context and not the Carolina Lithium site. Proportionally cropped and resized, then combined with the unchanged NCPN footer and logo.
Editor’s Note: This article was drafted with the assistance of artificial intelligence and was reviewed and fact-checked by a member of the NC Political News editorial team before publication.